Throughout 2026, Jakarta's Human Settlements, Spatial Planning and Land Agency (CKTRP) held clarification meetings on 57 buildings, served 23 notices over the certificate of fitness for function (sertifikat laik fungsi, SLF) and issued temporary or permanent cease orders against 8 buildings. Temporary orders target an expired SLF; permanent orders target buildings used without one (Lumban Tobing, 2026). In May 2026 a Jakarta council committee summoned the managers of 23 buildings and said 15 had no SLF, some because it had lapsed (Rachmadina, 2026).
The push followed a fire at a seven-storey office building in Kemayoran, Central Jakarta, on 9 December 2025 that killed 22 employees. A CKTRP witness told the court that the building's SLF had expired on 27 August 2020 and that no renewal had been filed (Budi, 2026a). The owner admitted failing to monitor the SLF, which had already lapsed when the building was let in 2023 (Nugraheny, 2026). On 21 May 2026 the tenant company's president director was sentenced to 1 year and 4 months for negligence causing death under Article 474(3) of the Criminal Code, the panel finding that he had ignored 6 aspects of occupational safety and health (OSH) facilities (Budi, 2026b). The South Jakarta sub-agency then inspected 650 buildings under eight storeys (Sakti, 2026).
This article maps the building approval (persetujuan bangunan gedung, PBG), the SLF, the electrical certificate of operational fitness (sertifikat laik operasi, SLO), statutory inspection of OSH equipment (riksa uji) and the environmental approval across the life of offices, plants and warehouses. Each article cited was read in the regulation in force in November 2026, and each permit has its own issuer and clock.
Four Legal Regimes
The building regime rests on Law Number 28 of 2002 on Buildings as amended by Law Number 6 of 2023 on Job Creation. Construction starts after a PBG is granted (Article 36A), use starts after an SLF is issued by the central or regional government, and maintenance and periodic inspection must keep the building fit for function (Article 37) (Republic of Indonesia, 2002, 2023). Government Regulation Number 16 of 2021 implements it and, among other things, requires a fire protection system in every building (Article 30) (Government of the Republic of Indonesia, 2021a).
The electricity regime rests on Law Number 30 of 2009 on Electricity, whose Article 44(4), as amended, requires every operating installation to hold an SLO (Republic of Indonesia, 2009, 2023). Minister of Energy and Mineral Resources Regulation Number 12 of 2021 requires an SLO for high- and medium-voltage installations, issued by the Minister with the help of an accredited technical inspection body (Lembaga Inspeksi Teknik, LIT) (Article 31), and for low-voltage installations, issued by a low-voltage LIT (Article 40) (Ministry of Energy and Mineral Resources [MEMR], 2021b).
The OSH regime rests on Law Number 1 of 1970 on Occupational Safety. Article 3(1) calls for requirements to prevent and extinguish fires, secure and maintain buildings and prevent electric shock, and Article 4(2) names testing and approval among them (Republic of Indonesia, 1970). Technical rules sit in ministerial regulations per equipment type, while testing and OSH certificates now follow Minister of Manpower Regulation Number 11 of 2026 on Labour Inspection Procedures (Ministry of Manpower [MoM], 2026a), amended by Regulation 15/2026 (MoM, 2026b) and compared in an earlier article.
The fourth regime is business licensing. Government Regulation Number 28 of 2025 makes the PBG and SLF basic requirements alongside spatial use conformity and the environmental approval (Article 12(1)) (Government of the Republic of Indonesia, 2025), and the environmental approval is a precondition for a business licence under Article 3 of Government Regulation 22/2021 (Government of the Republic of Indonesia, 2021b).
Duties by Lifecycle Stage
Planning and Construction
- The owner applies for the PBG through the building information system (SIMBG) before construction; the design goes to the regency or city, to the province in Jakarta, or to the central government, and is reviewed in a free planning consultation (Article 253) (Government of the Republic of Indonesia, 2021a).
- Electrical installations are planned through studies and an engineering design (Article 8 of MEMR Regulation 10/2021) (MEMR, 2021a).
- Lifting equipment is inspected and tested from design, manufacture and installation onwards (Article 173) (MoM, 2020).
Handover
- The regional technical agency issues the SLF through SIMBG within 3 working days of the supervisor's statement of fitness being uploaded, free of charge, and the owner must hold it before use (Articles 274 and 276) (Government of the Republic of Indonesia, 2021a).
- A new electrical installation is tested by a licensed inspection company and may operate only once it holds an SLO (Articles 15 to 18) (MEMR, 2021a).
- Elevators, lifting equipment and electrical installations receive a first test before use, which is the basis for a certificate of OSH compliance or non-compliance (Articles 40 and 45) (MoM, 2026a).
Routine Operation
- The owner or user inspects the building at the interval set by the technical standard, or at least every 6 months, and keeps a report (Article 295) (Government of the Republic of Indonesia, 2021a).
- The SLF of any building other than a detached or terraced house is renewed every 5 years, after a fitness inspection by a licensed technical assessor at the owner's or user's cost (Articles 297 and 298) (Government of the Republic of Indonesia, 2021a).
- A high- or medium-voltage SLO is valid for 10 years and a low-voltage SLO for up to 15 years, both renewable (Articles 39 and 44) (MEMR, 2021b).
- Workplace electrical installations are inspected at least yearly and tested at least every 5 years (Article 11) (MoM, 2015); elevators and escalators are inspected and tested at least yearly (Article 73) (MoM, 2017); cranes are tested no later than 2 years after the first test and yearly after that, and lifting accessories at least yearly (Article 176) (MoM, 2020).
Changes and Renovation
- A change of function or classification requires an amended PBG (Article 11(2)), as do changes to floors, area, facade or safety-related components (Article 262(2)); renovation needs a PBG before work starts (Article 296(10)) (Government of the Republic of Indonesia, 2021a).
- A reconditioned, modified, uprated or relocated electrical installation must be retested (Article 16) (MEMR, 2021a), and a low-voltage SLO lapses after such changes (Article 44(3)) (MEMR, 2021b).
- Relocation, an accident, serious damage, or equipment in use but never tested triggers a special test (Article 42(2)), and a certificate of OSH compliance lapses after an accident, serious damage or a change to the object (Article 45(8)) (MoM, 2026a).
- An existing building without a PBG obtains it through the SLF, processed together in SIMBG (Articles 286(2) and 346(3)) (Government of the Republic of Indonesia, 2021a).
Who Bears What
Building law puts the PBG and SLF on the owner, and periodic inspection, maintenance and repair on the owner or user (Article 41(2) of Law 28/2002 as amended) (Republic of Indonesia, 2023). Where a building has several owners or users, the appointed manager is responsible for maintenance and SLF renewal (Article 294) (Government of the Republic of Indonesia, 2021a). Law 1/1970 puts safety duties on the pengurus, who directly leads a workplace, and on the employer using it, including on premises it does not own (Article 1 points 2 and 3), and requires the pengurus to meet every requirement for the workplace (Article 9(4)) (Republic of Indonesia, 1970). A tenant therefore keeps its OSH duties in the space it uses, even though the SLF belongs to the owner.
Sanctions are layered. Law 28/2002 as amended provides administrative sanctions from written warnings to suspension of use, suspension or revocation of the PBG and SLF, and demolition orders (Article 45), and imprisonment of up to 3, 4 or 5 years with a fine set as a percentage of the building's value for owners or users whose breach causes property loss, permanent disability or death (Article 46) (Republic of Indonesia, 2023). Operating without an SLO in a way that causes casualties carries up to 5 years and a fine (Article 54 of Law 30/2009 as amended) (Republic of Indonesia, 2023). Since 2 January 2026, fines outside the Criminal Code have been adjusted by Law Number 1 of 2026 on the Adjustment of Criminal Penalties, detailed in an appendix we did not trace, so current fine levels should be checked before quoting (Republic of Indonesia, 2026). On the OSH side, failed equipment faces a prohibition or stop-work order until a compliance certificate is issued (Article 45(4) to (6)) (MoM, 2026a).
Recurring Gaps
Clause 6.1.3 of ISO 45001:2018 and ISO 14001:2015 asks organisations to determine applicable legal requirements and keep them current (International Organization for Standardization [ISO], 2015, 2018), and ISO 55001:2024 sets requirements for an asset management system (ISO, 2024). Read together, the register says what is required and asset management says when each duty arises. We see four gaps.
First, the SLF is treated as a one-off. PP 16/2021 sets a 5-year cycle for buildings other than detached and terraced houses, yet the Kemayoran SLF had lapsed more than five years before the fire with no renewal filed (Budi, 2026a), and the council's finding on 15 buildings points the same way (Rachmadina, 2026). At a hospital in Bogor, the SLF and the operating licence fell due almost together, so a delay in one held up the other (Churniadita et al., 2023). In Jember, many owners and managers did not yet understand why the SLF matters (Ratnaningsih et al., 2024). In our view the root cause is unclear task ownership, especially in leased buildings, where the renewal duty sits with the owner and the daily risk with the tenant.
Second, the asset changes but the permits do not. An office turned into a store or an added floor should trigger an amended PBG, and SLF renewal compares as-built drawings with the last SLF (Article 297(4) to (6)) (Government of the Republic of Indonesia, 2021a). Research in Bandung found buildings used in ways that did not match their permits and a lack of specific implementing guidance (Elora, 2021). In the Kemayoran case, prosecutors said the office also stored business goods, including lithium polymer batteries (Budi, 2026a). We draw no causal conclusion from that charge, but a change of use is a permit matter under building law.
Third, the SLO is seen as finished once power is connected. It has a validity period and, for low voltage, lapses when the installation is modified or reconditioned (MEMR, 2021b). The annual electrical OSH inspection under Regulation 12/2015 runs separately, so a switchboard can hold a valid SLO yet go uninspected after new machines are added (MoM, 2015). Jakarta's fire service recorded 649 of 1,216 fires from January to August 2026 as suspected electrical (Suciatiningrum, 2026). That is a field officer's suspicion, not a forensic finding, and says nothing about missing SLOs; we use it only to rank electrical installations first, as in our discussion of the Pasar Kemis fan factory fire.
Fourth, statutory inspections go overdue or equipment runs without a certificate. Annual cycles are the shortest after the building's own inspection, and so the most often missed. Regulation 11/2026 makes untested equipment in use a ground for a special test and voids the certificate after an accident, serious damage or a change (MoM, 2026a), while certificates issued earlier stay valid until they expire (Article 52) (MoM, 2026a).
The evidence has limits. No open national data show the share of buildings or installations with an expired SLF or SLO; the Jakarta figures count enforcement, not prevalence, and detailed results of the 650 South Jakarta inspections are unpublished (Sakti, 2026). The Kemayoran court facts come from news reports, not the judgment. We found no open data on insurance claims refused over an expired SLF or SLO, so we do not quantify that risk. Our view on task ownership is an interpretation of case patterns.
Sensible Next Steps
We drew these steps from the articles above:
- Build the obligations register per asset, not per regulation: asset or building part, required document, issuer, inspector, issue date, validity, renewal triggers and internal owner.
- Build the calendar from the shortest cycle: building inspection at least every 6 months, annual electrical inspection and equipment tests, the SLF and electrical testing every 5 years, and the SLO every 10 or 15 years. Start SLF renewal early, since a technical assessment comes first.
- Set priorities: buildings without a valid SLF; cranes, elevators and pressure vessels without a valid certificate; electrical installations changed since the last SLO; then environmental documents.
- Install a change gate: every renovation, change of use, added machine or relocation is checked first for an amended PBG, an installation retest and a special test.
- Involve the right parties: owner and building manager for the PBG and SLF, a licensed technical assessor for fitness inspections, an LIT for the SLO, a licensed OSH inspection company (PJK3) and labour inspectors for riksa uji, and legal counsel for leases. A lease should state who renews the SLF and who pays for OSH inspections in the leased space.
One belief needs correcting: that a certificate makes a building safe, when it only records the condition at inspection. The head of Jakarta's CKTRP Agency has said that a missing SLF does not automatically mean danger, but that safety must be confirmed by inspection rather than assumed (Lumban Tobing, 2026). What protects occupants is inspection, maintenance and change control between two certificate dates.
Third-Party Support
As a third party, the Nusa Safety team can help build the register of legal obligations and compliance calendar within SMK3 and ISO 45001 implementation, assess compliance gaps in buildings and assets through a building and facility safety assessment, coordinate documents and submissions for the PBG and SLF with licensed professionals and technical assessors in its partner network, and review fire and electrical safety through a FESA audit and an electrical system assessment. For OSH equipment, the team compiles the equipment list and test schedule and coordinates statutory inspection with licensed PJK3 partners.
The SLF is issued by the regional government, the SLO by or through the authorised technical inspection body, and riksa uji certificates by the competent manpower authorities, not by Nusa Safety. Nusa Safety is not a PJK3 and issues only internal training certificates. Legal questions on a specific case should go to an advocate; to discuss your needs, start from the contact page.
This article is general information and not legal or professional advice for any specific case.
References
- Budi, M. (2026a, April 15). Sertifikat laik fungsi kantor Terra Drone yang terbakar kedaluwarsa sejak 2020 [Certificate of fitness of the burned Terra Drone office expired in 2020]. detikNews. https://news.detik.com/berita/d-8445643/sertifikat-laik-fungsi-kantor-terra-drone-yang-terbakar-kedaluwarsa-sejak-2020
- Budi, M. (2026b, May 21). Vonis bos Terra Drone lebih rendah dari tuntutan, ini pertimbangan hakim [Terra Drone chief's sentence lower than prosecutors sought: the judges' reasoning]. detikNews. https://news.detik.com/berita/d-8498477/vonis-bos-terra-drone-lebih-rendah-dari-tuntutan-ini-pertimbangan-hakim
- Churniadita, N., Widiyaningsih, C., & Supardjo, S. (2023). Evaluasi pemenuhan persyaratan sertifikat laik fungsi gedung Rumah Sakit Palang Merah Indonesia tahun 2023 [Evaluation of certificate of fitness requirements at the Indonesian Red Cross Hospital building, 2023]. Jurnal Manajemen dan Administrasi Rumah Sakit Indonesia (MARSI), 7(3), 248-255. https://doi.org/10.52643/marsi.v7i3.3386
- Elora, D. (2021). Sertifikat laik fungsi pada bangunan gedung di Kota Bandung dalam kaitannya dengan izin mendirikan bangunan [Certificates of fitness for buildings in Bandung in relation to building permits]. Jurnal Ilmiah Universitas Batanghari Jambi, 21(3), 963. https://doi.org/10.33087/jiubj.v21i3.1687
- Government of the Republic of Indonesia. (2021a). Government Regulation Number 16 of 2021 on the implementing regulation of Law Number 28 of 2002 on Buildings. State Gazette of 2021 Number 26. https://peraturan.bpk.go.id/Details/161846/pp-no-16-tahun-2021
- Government of the Republic of Indonesia. (2021b). Government Regulation Number 22 of 2021 on environmental protection and management. https://pasal.id/peraturan/pp/pp-no-22-tahun-2021
- Government of the Republic of Indonesia. (2025). Government Regulation Number 28 of 2025 on risk-based business licensing. https://pasal.id/peraturan/pp/pp-no-28-tahun-2025
- International Organization for Standardization. (2015). ISO 14001:2015 Environmental management systems, requirements with guidance for use. https://www.iso.org/standard/60857.html
- International Organization for Standardization. (2018). ISO 45001:2018 Occupational health and safety management systems, requirements with guidance for use. https://www.iso.org/standard/63787.html
- International Organization for Standardization. (2024). ISO 55001:2024 Asset management, asset management system, requirements. https://www.iso.org/standard/83054.html
- Lumban Tobing, A. G. (2026, September 1). Jakarta cracks down on 23 buildings for functionality certificate lapses. Berita Jakarta, Jakarta Provincial Government. https://m.beritajakarta.id/en/read/155132/jakarta-cracks-down-on-23-buildings-for-functionality-certificate-lapses
- Ministry of Energy and Mineral Resources of the Republic of Indonesia. (2021a). Regulation of the Minister of Energy and Mineral Resources Number 10 of 2021 on electrical safety. State Bulletin of 2021 Number 538. https://jdih.esdm.go.id/storage/document/Permen%20ESDM%20Nomor%2010%20Tahun%202021%20tentang%20Keselamatan%20Ketenagalistrikan.pdf
- Ministry of Energy and Mineral Resources of the Republic of Indonesia. (2021b). Regulation of the Minister of Energy and Mineral Resources Number 12 of 2021 on the classification, qualification, accreditation and certification of electricity support services. https://pasal.id/peraturan/permen/permen-esdm-no-12-tahun-2021
- Ministry of Manpower of the Republic of Indonesia. (2015). Regulation of the Minister of Manpower Number 12 of 2015 on occupational safety and health for electricity in the workplace. State Bulletin of 2015 Number 540. https://jdih.kemnaker.go.id/peraturan/detail/610/peraturan-menteri-nomor-12-tahun-2015
- Ministry of Manpower of the Republic of Indonesia. (2017). Regulation of the Minister of Manpower Number 6 of 2017 on occupational safety and health for elevators and escalators. State Bulletin of 2017 Number 909. https://pasal.id/peraturan/permen/permenaker-no-6-tahun-2017
- Ministry of Manpower of the Republic of Indonesia. (2020). Regulation of the Minister of Manpower Number 8 of 2020 on occupational safety and health for lifting and transport equipment. State Bulletin of 2020 Number 609. https://pasal.id/peraturan/permen/permenaker-no-8-tahun-2020
- Ministry of Manpower of the Republic of Indonesia. (2026a). Regulation of the Minister of Manpower Number 11 of 2026 on labour inspection procedures. State Bulletin of 2026 Number 438. https://jdih.kemnaker.go.id/peraturan/detail/3070/peraturan-menteri-ketenagakerjaan-nomor-11-tahun-2026
- Ministry of Manpower of the Republic of Indonesia. (2026b). Regulation of the Minister of Manpower Number 15 of 2026 amending Regulation Number 11 of 2026 on labour inspection procedures. https://jdih.kemnaker.go.id/peraturan/detail/3109/peraturan-menteri-ketenagakerjaan-nomor-15-tahun-2026
- Nugraheny, D. E. (2026, April 22). Kebakaran tewaskan 22 orang, pemilik gedung Terra Drone akui lalai pantau SLF [Fire kills 22, Terra Drone building owner admits failing to monitor the SLF]. Kompas.com. https://megapolitan.kompas.com/read/2026/04/22/13201041/kebakaran-tewaskan-22-orang-pemilik-gedung-terra-drone-akui-lalai-pantau
- Rachmadina, R. (2026, May 26). DPRD DKI temukan 15 gedung tak miliki SLF: Ada hotel, kampus, hingga rumah sakit [Jakarta council finds 15 buildings without an SLF, including hotels, campuses and hospitals]. Kompas.com. https://megapolitan.kompas.com/read/2026/05/26/17274921/dprd-dki-temukan-15-gedung-tak-miliki-slf-ada-hotel-kampus-hingga-rumah
- Ratnaningsih, A., Putra Indarto, Y. M., & Sukmawati, S. (2024). Identifikasi faktor-faktor yang mempengaruhi kelaikan fungsi bangunan gedung terhadap sertifikat laik fungsi menggunakan diagram fishbone [Identifying factors affecting building fitness for function and the certificate of fitness using a fishbone diagram]. Teras Jurnal: Jurnal Teknik Sipil, 14(2), 574-588. https://doi.org/10.29103/tj.v14i2.1158
- Republic of Indonesia. (1970). Law Number 1 of 1970 on occupational safety. State Gazette of 1970 Number 1. https://pasal.id/peraturan/uu/uu-no-1-tahun-1970
- Republic of Indonesia. (2002). Law Number 28 of 2002 on buildings. State Gazette of 2002 Number 134. https://pasal.id/peraturan/uu/uu-no-28-tahun-2002
- Republic of Indonesia. (2009). Law Number 30 of 2009 on electricity. https://pasal.id/peraturan/uu/uu-no-30-tahun-2009
- Republic of Indonesia. (2023). Law Number 6 of 2023 on the enactment of Government Regulation in Lieu of Law Number 2 of 2022 on job creation into law. https://pasal.id/peraturan/uu/uu-no-6-tahun-2023
- Republic of Indonesia. (2026). Law Number 1 of 2026 on the adjustment of criminal penalties. https://pasal.id/peraturan/uu/uu-no-1-tahun-2026
- Sakti, T. S. (2026, July 3). South Jakarta CKTRP Sub-agency has checked 650 buildings suitability. Berita Jakarta, Jakarta Provincial Government. https://m.beritajakarta.id/en/read/153783/south-jakarta-cktrp-sub-agency-has-checked-650-buildings-suitability
- Suciatiningrum, D. (2026, September 22). Jakarta membara, kasus kebakaran tembus 1.216 hingga Agustus 2026 [Jakarta ablaze: fires pass 1,216 by August 2026]. IDN Times. https://www.idntimes.com/news/indonesia/jakarta-membara-kasus-kebakaran-tembus-1-216-hingga-agustus-2026-00-481xk-1qcgvh